Flooding Susitna River takes down 2nd transmission tower; river travelers once again cautioned
For the second time in a week a flooding Susitna River has disabled a transmission
line tower after undercutting its foundation at Dynamite Slough.
On Monday morning Chugach Electric Association discovered the river had undercut the
foundation under one leg of a transmission line tower on an island between the main channel
of the Susitna and a normally quiet stretch of water called Dynamite Slough. After weeks of
steady -- and sometimes heavy -- rains upstream in the Susitna Valley, the slough is now
running full of water with very strong current.
The 70-foot aluminum tower knocked askew on Monday supports a 230,000-volt transmission
line that carries power from Chugach's Beluga Power Plant. It is one of three transmission
lines that move power from Alaska's largest power plant for delivery throughout the Railbelt.
The tower is the second one in a week at the same location to be damaged by a raging Susitna
River. A similar tower on a parallel transmission line -- known to the utility as Beluga
Transmission Line No. 3 -- was eroded and fell in the river on the evening of Aug. 15. It
took Chugach a few days to safely stabilize that tower, free the wires and re-energize the line.
The most recent problem that affected the tower on Beluga Transmission Line No. 2 apparently
occurred some between early afternoon Sunday and late morning Monday. Chugach flew patrols of
the line at those times and days. Chugach has been closely monitoring the flooding since before
the first tower went down, and daily for the past week and a half. After Line No. 3 was returned
to service a few days ago, Chugach de-energized Line No. 2 knowing the water was threatening the
tower's foundation. Consequently, customers did not experience any power outages or blinking
lights when the tower tipped over. On Monday, the tower was leaning at about a 45-degree angle
over the river, held aloft by its electrical conductors.
Although the line is de-energized, the three wires that normally carry electricity are still
attached to the structure and are suspended approximately 10-15 feet above the Susitna River at
their low point. Persons traveling the river are cautioned to watch for the low wires. As it
did a week ago, Chugach notified both the Alaska State Troopers and the U. S. Coast Guard of the hazard.
Chugach is assessing the situation to determine the best way to safely separate the electrical
lines from the tower. With one line out of service, Chugach has reduced the output from the
Beluga Power Plant and is making or buying power from other generation resources in the region.
Even before the first tower went down, Chugach had been making plans to move towers further
back from the river. It has been something the utility has had to do many times since Lines 1,
2 and 3 were built in 1967, 1974 and 1981, respectively. Not counting the two towers that have
been eroded in the past week, Chugach estimates it has moved or replaced 15 towers in the past
15 years at river crossings between the Beluga Power Plant and Point MacKenzie.
Chugach is the largest electric utility in Alaska, providing power for Alaskans throughout the
Railbelt through retail, wholesale and economy energy sales.
|