Logocooper lake dam
box01cooper lake dam
filler




In 2002, Chugach Electric Association, Inc. (Chugach), initiated the process to relicense its Cooper Lake Hydroelectric Project (Project: FERC No. 2170). The Project is located near Cooper Landing on the Kenai Peninsula and provides power to southcentral Alaska as part of Chugach's generating system. The operating license for the Project was issued by the Federal Energy Regulatory Commission (FERC) on May 1, 1957. The existing license is scheduled to expire on April 30, 2007 and therefore, Chugach filed an application for a new license in April 2005.

Project Description

The Project is located on Cooper Creek, Cooper Lake, and Kenai Lake (Seward B-8 Quadrangle, Alaska). The powerhouse, penstock and intake structures are located on State-owned land. The Project dam and reservoir are located within the Chugach National Forest. The Project transmission line is located on lands owned by a number of different entities, including Chugach National Forest and the Alaska Department of Natural Resources.

The primary components of the Project are:

  • Cooper Lake Dam, a rock-and-fill structure across Cooper Creek at the outlet of Cooper Lake.
  • Cooper Lake, a natural lake that has been increased in area to 3,100 acres by the dam (Note: Since 1985, the water surface of the lake has been maintained at an elevation 16 feet below licensed normal maximum pool elevation for dam safety considerations; the current surface area of lake is 2,600 acres).
  • An intake structure, located approximately 5 miles southeast of the dam. Elevation of the invert of the opening to the tunnel/penstock is at 1,151 feet MSL (43 feet below the water surface at the current full pool elevation of 1,194 feet MSL).
  • A tunnel, conduit, and penstock extending 10,300 feet east from Cooper Lake to the Cooper Lake Powerhouse on Kenai Lake.
  • Cooper Lake Powerhouse, containing two turbine/generator units, each rated at 9.69 MW (upgraded from 7.5 MW in 2000).
  • A 6.3-mile-long 69-kV transmission line from the Cooper Lake Powerhouse to the Quartz Creek substation.
  • An 90.4-mile-long 115-kV transmission line from the Quartz Creek Substation to the Anchorage Substation.

Summary of Project Operations

The Project stores all inflow to Cooper Lake and diverts the entire natural outflow from the lake through the tunnel/penstock and to the powerhouse, which discharges into Kenai Lake. The diverted natural flow ranges on average from around 8 cfs during late winter / early spring to about 280 cfs during early summer snowmelt, based on calculated inflows to Cooper Lake. Average annual inflow to / discharge from the lake is approximately 72,500 acre-feet. Electricity generated at the powerhouse (which averages approximately 50,500 megawatt hours [MWh] per year) is transmitted to the Quartz Creek Substation, from where it is transferred to and distributed along the transmission line to the Anchorage Substation.

Key Resource Areas and Issues

The environmental setting of the Cooper Lake Project encompasses a number of different resource areas, including water use and quality, fish resources and aquatic habitat, terrestrial resources (vegetation and wildlife), cultural resources (archaeological and historical features), recreation resources, land use and management, and aesthetic/visual resources. Information in each of these resource disciplines will be compiled and analyzed, through research and field studies as needed, to fully address potential impacts of ongoing Project operations on the environment. Based on discussions to date with agencies and other relicensing participants, the resource areas and issues of primary concern involve fisheries and aquatics-related effects associated with the Project's diversion of all former Cooper Lake flow into Cooper Creek through the powerhouse on Kenai Lake and fluctuating lake levels on Cooper Lake. Terrestrial resource issues related to fluctuating lake levels also have been identified as a concern.

Overview of the Relicensing Process

Description of Process

Chugach has elected to use a relicensing process that is formally structured according to the traditional three-stage consultation process, but which also incorporates a number of enhanced consultation aspects beyond the formal requirements of the traditional process. The intent of this "enhanced traditional" relicensing process is to provide higher quality opportunities for exchanging information with relicensing participants than would be afforded under a strictly traditional process. Chugach's hope is that the open, participative relicensing process that it is using will increase the potential for a mutually acceptable relicensing outcome, by involving stakeholders in the scoping of relicensing issues, the design of relicensing studies, the assessment of ongoing Project effects and the identification of potential protection, mitigation and enhancement (PME) alternatives.

Formal Consultation Milestones and Schedule

FERC-required relicensing steps in the traditional process, from issuance of the Initial Consultation Package (ICP) through FERC's processing of the final license application and conducting of the NEPA analysis, are summarized below.

Any applicant for a new hydropower license is required to submit to FERC a Notice of Intent (NOI) to relicense the project. The NOI must be filed five years prior to the end of the existing license. Chugach filed its NOI with FERC on February 25, 2002 (a copy of the NOI is posted under the "Documents" section of this web site). Under the traditional relicensing process, consultation with agencies and other stakeholders on the relicensing is conducted in three stages. First-stage consultation is initiated with issuance of the ICP (targeted for early June 2002), which summarizes existing information relevant to the relicensing and identifies potential studies to be conducted. A public meeting / site visit is required to be held within 30-60 days of issuance of the ICP (this meeting / site visit is targeted for mid-July 2002). After a 60-day review period following the site visit, agencies and other stakeholders provide written comments on the ICP, including requests for studies to be conducted. First-stage consultation also includes development of resource-specific study plans. Chugach anticipates that first-stage consultation will continue through early 2003.

Second-stage consultation involves conducting studies, issuance of the draft license application, and documentation of consultation on the draft application. The draft license application needs to be issued approximately one year ahead of the filing date for the final license application, to allow time for the formal 90-day comment period on the draft application, the required "substantive disagreement" meeting within 30 days of the close of the comment period, and revision and finalization of the license application. Chugach anticipates that the draft license application will be issued for comment in the second quarter of 2004.

Third-stage consultation begins with filing of the final application, no later than April 30, 2005. After it receives the final application, FERC evaluates the application for completeness and then conducts its NEPA analysis. Third-stage consultation includes further opportunities for stakeholder comment on the application in the context of FERC's NEPA analysis.

The current relicensing schedule for the Cooper Lake Project is available for viewing, including the timelines for the various formal process requirements described above.

Additional Proposed Interactions with Participants

In addition to the steps formally required under the traditional relicensing process, Chugach has outlined further measures aimed at engaging relicensing participants in additional consultation throughout the relicensing process. These proposed additional consultation opportunities include informational meetings and workshops, input to study approaches, review of draft study plans and reports, and potential formation of resource-specific work groups. Some of these planned consultation points are shown in relation to the formal consultation milestones in the relicensing schedule.

To further facilitate information exchange with relicensing participants, Chugach has established this relicensing web site. This web site will be used to post items such as meeting agendas, documents (e.g., study plans, reports, and meeting summaries), and other information related to the relicensing. In addition, a summary of the relicensing consultation record has been developed for this web site, and will be updated on a regular basis.

Summary

Through its planned process for relicensing the Cooper Lake Project, beginning with preliminary interactions with relicensing participants and continuing with issuance of the ICP and subsequent meetings and workshops, Chugach hopes to conduct an open and participative process that will strengthen existing working relationships among all the relicensing participants and ultimately result in a new license for the Project that allows for both continued operation of this important regional source of electricity as well as protection of the important environmental resources associated with the Project.

Relicensing Participants

Chugach has developed a list of participants in this relicensing process, based on agencies'/organizations' and individuals' past interest and involvement in activities related to the Cooper Lake Project. Click here to view the current list of relicensing participants. Organizations and individuals on this list will receive regular mailings regarding the relicensing, including relicensing documents issued to the public and invitations to meetings, workshops, and other events. If you would like to be added to the list of relicensing participants, fill out the relicensing participant contact information form and submit to Chugach.

List of relicensing participants (including contact information)

Contact Information

Questions or comments on the Cooper Lake relicensing may be sent to relicensing@chugachelectric.com.


Cooper Lake Relicensing Project


box03