Projects

Land-use Action for Projects

Chugach has several land-use actions underway or pending to enable future projects or in one case, to remedy an adverse result of a prior project. Chugach has been discussing the following projects with neighborhood councils, municipal officials and others.

Girdwood Substation

Since the 1990s, Chugach has owned four vacant lots adjacent to the Girdwood Substation. This summer Chugach will seek a conditional use permit for three of the unused lots to accommodate improvements to the substation, including the installation of new switchgear.

Information on the Girdwood Substation Upgrade

Dowling Substation land swap

Chugach is still working with the Municipality of Anchorage on a solution for land lost at the Dowling Substation to a recent road project. Chugach is seeking an equal amount of land to enable future improvements to be made at the substation, located near the intersection of Dowling and Elmore roads.

Girdwood Second Feeder

Chugach is installing a second feeder in the Girdwood area.  The new feeder will be an underground 350 MCM Aluminum conductor installed in conduit from the existing Girdwood Substation located just off Seward Highway.  The feeder will extend north between the Alyeska Highway and Glacier Creek, cross the river at the bridge, and tie into the existing underground system near Donner Drive.

Girdwood Substation Upgrade

Chugach operates a substation on lots 17 and 18, Block 3, Girdwood Original Townsite. This substation has been in operation since the early 1970s. Plans for an expansion of this station in the 1990s led to the purchase of Lots 19 to 22 adjacent to, and north of the existing station. The upgrade plans were postponed, when the availability of natural gas slowed the growth of demand for electric energy in the community.

Condition and age of equipment installed in the station now make it necessary to replace the low voltage (25kV) open-air switchgear as well as the control enclosure. In order to accommodate future load growth and increase service reliability, Chugach plans to install 25kV switchgear in a metal enclosure. It will also include the controls for the high voltage (115kV) switchgear and other auxiliary equipment, such as batteries, chargers and low voltage power panels.

Load forecasts indicate that a second transformer will need to be installed between 2020 and 2025. At that time, the existing high voltage switching arrangement will not be adequate to maintain reliable service. It will be upgraded to allow termination of a looped 115kV circuit with a circuit breaker to separate line sections and taps to 2 transformers. This will occupy most of 5 (Lots 17 to 21) of the 6 lots. A wooden fence and planting of shrubs on the exposed sides of the station will enhance the appearance.

The present zoning of the additional area required for the full build out of the substation is gC-3, which allows the substation upgrade under a conditional use permit issued by the Municipality of Anchorage.

In 2009 Chugach evaluated alternative sites for a substation. In early 2010 Chugach presented the results of that study to the Girdwood Board of Supervisors. Chugach is seeking a Conditional Use Permit for the project on land it owns adjacent to the existing substation.

Schedule

Submit Conditional Use Permit Application October 2010
Receive Conditional Use Permit December 2010
Procure Equipment 2011
Construct Upgrade 2012/13

Proposed Development

Southcentral Power Project

The Southcentral Power Project (SPP) is a joint project with Municipal Light & Power (ML&P) to construct a new efficient, gas-fired power plant located adjacent to Chugach's existing International Station at 5601 Electron Drive in Anchorage, Alaska.

Distribution Facilities Undergrounding Plan 2012 - 2016

On March 1, 2005, the Anchorage Assembly adopted certain revisions to Section 21.90, Utility Distribution Facilities, of the Anchorage Municipal Code. These revisions required an electric utility to "include as part of its annual capital improvement plan, a five-year undergrounding program." In each of the years of this program the electric utility shall plan on expending "at least two percent of a three-year average of its annual gross retail revenues derived from utility service connections within the municipality". This requirement means that Chugach Electric Association (Chugach) is required to spend approximately $3.2 million annually to underground existing overhead facilities. Over expenditures or under expenditures may be carried over as an adjustment to the following year's obligation.

In the development of the five-year undergrounding program the electric utility is allowed to choose which existing lines to underground. Specifically, priorities for the program "shall be based on undergrounding in conjunction with the utility's essential system improvements and then by target areas."

The undergrounding plan lists the projects in Chugach's five-year undergrounding program. Overall, the plan calls for $16,350,000 to be expended on undergrounding existing overhead lines from 2012 to 2016, for an average of $3,270,000 annually.

The projects were chosen taking into account Chugach's overall system needs and consideration of the designated target areas. The inclusion of a project within this plan does not guarantee that the project will be constructed in the designated year.

Fire Island Wind Power

For the last 15 years, Chugach Electric actively pursued and assessed wind resource potential and development throughout our service territory, including the wind resource potential of Fire Island. Over the last several years, Chugach has been conducting the necessary studies to provide the insight we need to evaluate the project impact on our system and consumers.

Cooper Lake Hydroelectric Project Home

In 2007, the Chugach Electric Association, Inc. (Chugach) Cooper Lake Hydroelectric Project was issued a new operating license (Project: FERC No. 2170). The Project is located near Cooper Landing on the Kenai Peninsula and provides power to southcentral Alaska as part of Chugach's generating system. The first operating license for the Project was issued by the Federal Energy Regulatory Commission (FERC) on May 1, 1957. The new 50-year license is scheduled to expire in 2057.

Project Home

Hope Line Relocation Study

The Chugach Electric Association, Inc., (Chugach) single-phase power distribution line serving the community of Hope, Alaska, and the surrounding area experiences frequent and lengthy power outages as a result of the terrain and climate the line encounters. The line originates at Chugach's Hope Substation, located near the Hope Highway Cutoff at Seward Highway milepost 56, and runs approximately 17.7 miles through Chugach National Forest and Department of Natural Resource (DNR) Land to the community of Hope. The line currently serves approximately 200 metered locations.

REPORT TO THE DENALI COMMISSION - Project 121-DC-2004-19